GO Transit disruptions continue following Monday derailment. Derailed train removed, but track and signal issues still hamper full schedule.
TORONTO — Missing screws holding track fasteners led to the derailment that disrupted GO Transit operations for a week, the CEO of provincial transit agency Metrolinx told the agency’s board at a ...
Significant GO Transit delays are expected to continue into the evening after a train derailed west of Union Station on Monday morning, Metrolinx says.
A train was departing Union Station Monday morning when it derailed, resulting in systemwide delays and cancellations.
GO Transit’s operating problems from a Monday derailment will extend into a fifth day, with the commuter rail service continuing to run a reduced schedule through Friday, provincial transit agency ...
GO Transit has been operating on a reduced schedule since a train came off its track near Union Station Monday, Feb. 2.
A disabled train near Union Station is causing mass train delays Monday, GO Transit says. TTC subway service downtown is also experiencing service disruptions.
Metrolinx says most track repairs at Union Station are complete, but significant signal damage will continue to affect GO Transit service in the coming days. Metrolinx says service will be reduced on ...